Bee Branch Creek Railroad Culverts
The City received $9 million to install six 8-foot diameter culverts utilizing tunneling methods from the Lower Bee Branch Creek, approximately 165 feet through the Canadian Pacific railroad right-of-way, to a proposed junction box. It also includes the construction of five 12-foot wide by 10-foot high box storm sewers from the proposed junction box two hundred feet north toward Garfield Avenue and the Upper Bee Branch Creek. The total cost for this component of the Bee Branch Project is estimated at $18 million, with the remaining funds already in the City budget.